Turkey wiil complete Syria border wall within 5 months

Turkey wiil complete Syria border wall within 5 months
A wall along the border between Turkey and Syria is pictured near the southeastern town of Deliosman in Kilis province, Turkey, August 29, 2016. REUTERS/Umit Bektas/File Photo

A concrete wall being built to stop illegal crossings along the length of Turkey’s 900-km (560-mile) border with Syria will be finished by the end of February, an official at a Turkish state institution with knowledge of the project said on Wednesday.

Ankara has long been under pressure from its NATO allies to seal off the border with Islamic State-controlled territory in Syria and is also concerned by the presence of the Syrian Kurdish YPG militia, which controls most of its Syrian border.

Construction on a border wall to combat smuggling and illegal migration started as early as 2014 even as Turkey maintained an open-border policy that has seen nearly 3 million Syrians seek refuge in the country.

“Construction will be completed within five months,” the official told Reuters, declining to be identified because he was not authorized to speak to the media. He said winter conditions would be a challenge to the timetable, however.

A 200-km (125-mile) stretch of the wall has already been completed and state housing developer TOKI will build the rest, the official said. The official declined to give an estimate for the cost of construction. But the mass circulation Hurriyet newspaper said that including a road for military patrols planned alongside it, the wall was expected to cost 2 billion lira ($672 million).

The official declined to give an estimate for the cost of construction. But the mass circulation Hurriyet newspaper said that including a road for military patrols planned alongside it, the wall was expected to cost 2 billion lira ($672 million).

“As far as our national security is concerned, the increase of border security with Syria carries huge importance. With the completion of the wall, our border will become more secure,” said Ergün Turan, the head of TOKI, adding that the concrete blocks would cover the entire border with their two-meter-wide and three-meter-high dimensions

Made up of seven-tonne portable blocks topped with razor wire, the wall will be three meters (10 feet) high and two meters (6.5 feet) wide. The official said private companies would be hired once construction tenders were completed.

“We build the walls in a way that they can be moved away in the future if needed and as TOKİ they were not only dealing with pouring the cement and assembling the concrete but are also building a road behind the wall,” Turan added.

Hurriyet cited Turan as saying that 200-250 concrete blocks were currently being produced daily at five work sites, and that the latest construction work had begun around 20 days ago.

“When we say border, there is no road or anything there. As TOKİ, we open the roads. The job is not easy, we are working on mined fields,” Turan said, adding that Turkey was in a special situation as there were few countries in the world which shared a 900-kilometer-long border with a single country.

New watchtowers on roads patrolled by armored vehicles have already been erected along the border this year as part of increased security measures.